STA Mastery · All levels
ECO Regression Matrix: Expanded Case Study
Expanded Case Study for ECO Regression Matrix.
Extended case study
Signoff review: corners re-run, new violations introduced, signoff delta fails after an apparently minor change affecting ECO Regression Matrix.
Background
Team had closure last week on full MMMC matrix. New run shows regression clustered in one path group.
Symptoms observed
corners re-run, new violations introduced, signoff delta regression
Disagreement between synth and STA WNS
Hold violations after setup ECO
Investigation timeline
Hour 0: freeze netlist, SDC, SPEF, lib tags
Hour 1: diff constraints and run manifest
Hour 2: isolate corner/mode that fails
Hour 3: read worst path — cell vs net, clocks
Hour 4: classify root cause
Hour 5: minimal ECO or SDC fix
Hour 6: full regression + signoff memo
Root cause
Root cause tied to ECO Regression Matrix: Every ECO must re-run the agreed MMMC matrix plus SI; regression hygiene prevents shipping a fix that breaks another corner.
Fix and validation
Bounded ECO or audited SDC change
Re-run regression manifest, corner comparison table, signoff approval
Full MMMC + SI regression
Lessons learned
Tag every run
Diff constraints before blaming PD
Setup and hold together
CASE STUDY — ECO Regression Matrix
baseline WNS / regressed WNS / post-fix WNSSequence under stress
TIMING PATH — ECO Regression Matrix
launch FF --logic stages--> capture FF
| |
launch clock capture clock
| |
required: arrival < capture_edge - setup
metric: corners re-run, new violations introduced, signoff deltaSTA deep dive
ECO without regression is a coin flip.
Concept diagram
ECO LOOP
failing path -> fix -> setup check -> hold check -> SI -> MMMC matrixMetric graph
ECO PROGRESS
WNS
0 | o target
-50| o
-100| o baseline
+-----------------> ECO #Reports and artifacts
pre/post WNS
hold delta
leakage delta
ECO ticket log
Mini case study
48-hour tapeout crunch: VT swap fixed setup; hold fixed with route on short path — order mattered.
Debug branches
Never ship setup-only proof
Logical ECO needs equivalence
Senior review question
Ask: what corner/mode/view proves this topic is closed or failing?
Key takeaways
State corner, mode, view, and database tag with every slack claim.
Run setup and hold plus MMMC regression after every ECO.
Common pitfalls
Comparing STA runs with different SPEF or SDC tags.
Broad false_path to green-wash violations.
Setup-only ECO without hold check.
Principal STA review addendum
Every ECO must re-run the agreed MMMC matrix plus SI; regression hygiene prevents shipping a fix that breaks another corner.
Metric: corners re-run, new violations introduced, signoff delta