Extended case study

Signoff review: WNS, TNS, path slack distribution, failing endpoint count fails after an apparently minor change affecting Graph Traversal & Slack.

Background

Team had closure last week on full MMMC matrix. New run shows regression clustered in one path group.

Symptoms observed

  • WNS, TNS, path slack distribution, failing endpoint count regression

  • Disagreement between synth and STA WNS

  • Hold violations after setup ECO

Investigation timeline

  1. Hour 0: freeze netlist, SDC, SPEF, lib tags

  2. Hour 1: diff constraints and run manifest

  3. Hour 2: isolate corner/mode that fails

  4. Hour 3: read worst path — cell vs net, clocks

  5. Hour 4: classify root cause

  6. Hour 5: minimal ECO or SDC fix

  7. Hour 6: full regression + signoff memo

Root cause

Root cause tied to Graph Traversal & Slack: STA builds a timing graph of cell and net arcs; setup slack = required time − arrival time along the worst path.

Fix and validation

  • Bounded ECO or audited SDC change

  • Re-run report_timing -path_type full, slack histogram, path schematic

  • Full MMMC + SI regression

Lessons learned

  • Tag every run

  • Diff constraints before blaming PD

  • Setup and hold together

diagram
CASE STUDY — Graph Traversal & Slack
baseline WNS / regressed WNS / post-fix WNS

Sequence under stress

diagram
TIMING PATH — Graph Traversal & Slack

launch FF --logic stages--> capture FF
     |                           |
  launch clock                capture clock
     |                           |
  required: arrival < capture_edge - setup
  metric: WNS, TNS, path slack distribution, failing endpoint count

STA deep dive

Slack is a path story — read the graph, not just the number.

Concept diagram

diagram
TIMING GRAPH

FF --cell-- logic --net-- logic --cell-- FF
launch                              capture

Metric graph

diagram
SLACK TAIL

paths |    ***
      |  *******
      |*********  <- fix WNS first

Reports and artifacts

  • WNS/TNS

  • path slack histogram

  • cell vs net %

  • path group summary

Mini case study

WNS -90ps but 80% net delay on one congested route — PD route fix beat upsizing three cells.

Debug branches

  • Cell-heavy -> sizing/VT

  • Net-heavy -> route/layer

  • Check launch/capture clocks

Senior review question

Ask: what corner/mode/view proves this topic is closed or failing?

Key takeaways

  • State corner, mode, view, and database tag with every slack claim.

  • Run setup and hold plus MMMC regression after every ECO.

Common pitfalls

  • Comparing STA runs with different SPEF or SDC tags.

  • Broad false_path to green-wash violations.

  • Setup-only ECO without hold check.

Principal STA review addendum

STA builds a timing graph of cell and net arcs; setup slack = required time − arrival time along the worst path.

Metric: WNS, TNS, path slack distribution, failing endpoint count