Scenario: ECO Under Pressure
Critical path is reg2reg through congested region. PD proposes sizing; synthesis proposes VT swap; STA lead must choose minimal-risk ECO order.
Scenario
Critical path is reg2reg through congested region. PD proposes sizing; synthesis proposes VT swap; STA lead must choose minimal-risk ECO order.
OBSERVED METRIC
setup WNS -120ps with tapeout in 48 hours
45-MINUTE INTERVIEW FLOW
0-5: clarify corner/mode/view and path group
5-15: read critical path and constraints
15-25: classify constraint vs view vs real path
25-35: propose ECO order (setup/hold/SI)
35-45: state MMMC regression and signoff criteriaCommon pitfalls
Fix setup without hold check
Skip SI re-run
No regression matrix
Scenario debrief
Score: corner/mode, path group, constraint check, ECO, regression.
constraints -> graph -> slackWNS trendDebrief prompts
Which scenario failed first?
Setup, hold, or both?
What regression did you mandate?
Key takeaways
State corner, mode, view, and database tag with every slack claim.
Run setup and hold plus MMMC regression after every ECO.
Common pitfalls
Comparing STA runs with different SPEF or SDC tags.
Broad false_path to green-wash violations.
Setup-only ECO without hold check.